Search Posts
Recent Posts
- Rhode Island Weather for Dec. 23, 2024 – Jack Donnelly December 23, 2024
- Business Beat: BankNewport named RI SBA Lender of the Year December 23, 2024
- The wall of separation, church and state – Herb Weiss December 23, 2024
- Christmas past. Christmas present. Failing the homeless, we see our future. December 23, 2024
- Ask Chef Walter: Bocconotto from Abruzzo – Walter Potenza December 23, 2024
Categories
Subscribe!
Thanks for subscribing! Please check your email for further instructions.
RI construction season starts with $1.4 billion for these roads and bridges
Governor Dan McKee joined U.S. Senators Jack Reed and Sheldon Whitehouse, Congressmen James Langevin and David Cicilline and RIDOT Director Peter Alviti, Jr. to kick off the start of RIDOT’s 2021 construction season. The event was held under the Providence Viaduct, a sprawling structurally deficient bridge in our state’s capital city.
The $265 million Providence Viaduct Northbound project is one of RIDOT’s largest construction projects. It will replace a 1,300-foot bridge that carries more than 220,000 vehicles a day, making it the busiest stretch of highway in Rhode Island. It also will rebuild 10 bridges and correct inefficiencies, congestion and safety issues along this part of I-95 as part of a $60.3 million INFRA. There are 34 projects targeted, including 129 bridges. This year, the Department expects to have a total of 50 projects under construction, including 146 bridges with a total project cost of $1.4 billion.
“Infrastructure has always been a crucial component of Rhode Island’s economy, and it will be essential to our state’s economic recovery,” said Governor Dan McKee. “These projects will not only create good paying construction jobs, but also safe, updated and resilient infrastructure for our residents and businesses. I thank our Congressional delegation for helping us secure these federal funds. I look forward to continuing to improve and invest in our infrastructure to create strong communities and improve the quality of life for hardworking Rhode Islanders.”
“Rhode Island’s bridges and roads get a lot of wear and tear. They have long been in need of repair and I’m pleased to deliver a sustained increase in federal investments to enhance our transportation network. These projects are about more than asphalt and steel beams – they’re about making long-term infrastructure improvements that benefit communities and better connect people to jobs and opportunities,” said Senator Reed, a member of the Appropriations Committee. “These projects will improve safety and efficiency while reducing congestion and emissions. And new federal funds will put people to work this spring and summer and spur future economic growth by bringing more jobs, businesses, visitors, and commerce to Rhode Island.”
“The overhaul of the Northbound Viaduct is the centerpiece of RIDOT’s 2021 construction season,” said Senator Whitehouse, noting the job-creating goal and saying, ” The Viaduct will be transformed into a modern throughway with the capacity for hundreds of thousands of vehicles to safely and smoothly cross each day.”
“I was so proud to be with Governor McKee, Director Alviti, and my Congressional colleagues today to mark the start of construction season. Congressman Langevin noted the I-95 corridor will be safer and less congested for the 200,000+ drivers that use the Viaduct every day…while today was an important milestone to celebrate, our work is far from over. I’ll continue fighting in Congress to repair our aging infrastructure and create more good-paying jobs for Rhode Island.”
“Rebuilding our infrastructure is key to restoring the middle class,” Congressman Cicilline said.
“Here we go with another year of road and bridge construction happening in all corners of Rhode Island,” RIDOT Director Peter Alviti, Jr. said. “We are putting billions of dollars of improvements into the ground now with some long-awaited projects supported by more than $430 million in grants secured by our Congressional delegation.”
RhodeWorks now enters its 5th year, with 224 projects, and an investment of $2.6 billion. This included completion of 171 projects, including 167 bridges.
In addition to the Providence Viaduct Northbound project, highlights of the 2021 construction season include:
Route 6/10 Interchange – RIDOT is entering its third full year of construction on this $410 million project, RIDOT’s largest. It will address 11 bridges in total, replacing seven structurally deficient bridges. The project also features construction of the critical “missing move” to connect Route 10 North to Route 6 West – which may open by the end of 2021. RIDOT has completely removed traffic from five of the seven deficient bridges and has partially removed traffic from another. The project will finish in fall 2023.
Henderson Bridge: Demolition is underway on the westbound lanes on this $84.4 million project. By replacing this bridge which spans the Seekonk River from East Providence to Providence, RIDOT will reduce its statewide structurally deficient bridge area by 12 percent. The Henderson Bridge and Henderson Expressway were overbuilt as they were originally constructed as part of an unfinished highway. When finished in summer 2025, the bridge will feature two westbound lanes and one eastbound lane, as well as 2,500 feet of separated bike/pedestrian path infrastructure. The smaller footprint will require less maintenance and will free up almost 33 acres for potential development and recreational use.
Washington Bridge: RIDOT expects to select a design-build team for a $70 million project to rehabilitate the portion of the Washington Bridge that carries I-195 West traffic from East Providence to Providence over the Seekonk River. In addition to rehabilitating the bridge, the base technical concept includes an additional through lane to better accommodate mainline highway traffic and the high volume of traffic entering the highway from Veterans Memorial Parkway, Warren Avenue and Taunton Avenue ramps. A new exit ramp in East Providence will provide a direct connection to Waterfront Drive, a major area for future economic development on the East Providence waterfront, and an additional safe and convenient way for commuters to access the East Side of Providence. The existing Gano Street off-ramp will be retained. Pre-construction activities should begin this summer and the project will take four years.
Route 37 Bridges: Work is underway on 15 bridges on Route 37 from Post Road in Warwick to the Pontiac Avenue interchange. The project will make improvements to ease congestion and improve safety at the Pontiac Avenue interchange ($58.9 million).
Pawtucket/Central Falls Train Station and Bus Hub: Construction is underway on the $58 million project and trains are expected to start service in summer 2022 with an estimated 520 daily boardings, attracting ridership from Rhode Island and nearby South Attleboro where the MBTA recently closed one of its stations.
Providence-to-Newport Ferry: Service will resume this summer on this popular alternative to driving and parking in congested downtown Newport. The ferry has carried more than 175,000 people in its first five years.
Now that construction season has started, Rhode Islanders can expect to see more work zones from road and bridge construction work. Motorists may need to plan extra travel time but should know RIDOT plans the timing and duration of work zones to reduce as much as possible the impact to traffic flow and travel time.
Safety is RIDOT’s highest priority, and all work zones are established with careful attention to safety and in coordination with national standards and best practices.
Learn more at www.ridot.net/RhodeWorks.