SouthCoast Wind anticipates 4-year delay for offshore wind farm – Nantucket Current

Image, top, SouthCoast Wind, Nantucket CurrentColin A. Young, State House News Service • Feb 27, 2025

Officials behind the SouthCoast Wind project are no longer committing to start construction by the end of 2025, and it could be delayed until 2029 based on the uncertainty President Donald Trump has injected into the industry, the head of one of the 50-50 owners of the project said Wednesday.

“We had basically the project ready to go. Now, obviously given everything that’s come out over the last couple of weeks in terms of executive orders, and sort of them asking to also review the federal permits, we’ve decided to just be more prudent around the timing,” Miguel Stilwell d’Andrade, CEO of the Portuguese developer EDP Renewables, said in response to a question on an investor call. “Recognize that already in terms of [profit and loss] if we get a better scenario, then that would be great, but we’ve, let’s say, taken the more prudent four-year delay approach. [We] could have taken a two-year delay, but we took a four-year one. So we still have the project ready to go, and we’ll try to, say, manage that optionality.”

EDP Renewables and Engie, the other half of the Ocean Winds joint venture, wrote down the value of their U.S. offshore wind projects by $267 million (or about $139 million each) based on the potential that SouthCoast Wind may not get underway until 2029. Stilwell d’Andrade called a four-year delay for SouthCoast Wind “a slightly worst case scenario,” and other project officials stressed that the financial reporting does not mean the project will definitely be delayed.

“The impairment decision is a precautionary measure based on a scenario of potential delays in its projects,” Michael Brown, CEO of OW North America, said in a statement. “Ocean Winds strongly believes in the potential of offshore wind to generate significant economic activity and provide abundant, domestic energy to meet rapidly growing demand in the U.S. and remains confident in finding a path forward in coordination with all relevant authorities in the upcoming months.”

The Executive Office of Energy and Environmental Affairs did not respond to a request for comment Thursday.

SouthCoast Wind’s bid document referred to the 1,287 megawatts pledged to Massachusetts and Rhode Island as a “fully bankable project ready to start construction in 2025” and project officials said they anticipated being able to deliver power in 2030. On its final business day, the Biden administration announced that it approved the project’s crucial construction and operations plan.

An executive order President Trump signed last month essentially halted all federal offshore wind actions “pending the completion of a comprehensive federal review of federal wind leasing and permitting practices.”

Brown said the decision to write down U.S. wind assets shows Ocean Winds’ “commitment to maintaining transparency and financial discipline in a context where the impact of any changes in U.S. regulations, and specifically the Executive Order of 20 January 2025, is not yet known.”

Massachusetts in September selected 1,087 MW of the 1,287 MW SouthCoast Wind project, with the remaining 200 MW going to Rhode Island. The Bay State also chose to take the entire 791 MW New England Wind 1 project and up to 800 MW of the 1,200 MW Vineyard Wind 2 project at the same time, though the Vineyard Wind 2 project has been taken off the table.

Contracts are to be executed by March 31 and filed by May 9, though deadlines have repeatedly been extended. Project pricing information is expected to be made public when the contracts are filed.

_

Publisher’s Note: Here is the content of the Executive Order of January 20th, 2025:

Section 1.  Temporary Withdrawal of Areas.  Consistent with the principles of responsible public stewardship that are entrusted to this office, with due consideration for a variety of relevant factors, including the need to foster an energy economy capable of meeting the country’s growing demand for reliable energy, the importance of marine life, impacts on ocean currents and wind patterns, effects on energy costs for Americans –- especially those who can least afford it –- and to ensure that the United States is able to maintain a robust fishing industry for future generations and provide low cost energy to its citizens, I hereby direct as follows:

Under the authority granted to me in section 12(a) of the Outer Continental Shelf Lands Act, 43 U.S.C. 1341(a), I hereby withdraw from disposition for wind energy leasing all areas within the Offshore Continental Shelf (OCS) as defined in section 2 of the Outer Continental Shelf Lands Act, 43 U.S.C. 1331.  This withdrawal shall go into effect beginning on January 21, 2025, and shall remain in effect until this Presidential Memorandum is revoked.

To the extent that an area is already withdrawn from disposition for wind energy leasing, the area’s withdrawal is extended for a time period beginning on January 21, 2025, until this Presidential Memorandum is revoked.

This withdrawal temporarily prevents consideration of any area in the OCS for any new or renewed wind energy leasing for the purposes of generation of electricity or any other such use derived from the use of wind.  This withdrawal does not apply to leasing related to any other purposes such as, but not limited to, oil, gas, minerals, and environmental conservation.

Nothing in this withdrawal affects rights under existing leases in the withdrawn areas.  With respect to such existing leases, the Secretary of the Interior, in consultation with the Attorney General as needed, shall conduct a comprehensive review of the ecological, economic, and environmental necessity of terminating or amending any existing wind energy leases, identifying any legal bases for such removal, and submit a report with recommendations to the President, through the Assistant to the President for Economic Policy.

Sec. 2.  Temporary Cessation and Immediate Review of Federal Wind Leasing and Permitting Practices.  (a)  In light of various alleged legal deficiencies underlying the Federal Government’s leasing and permitting of onshore and offshore wind projects, the consequences of which may lead to grave harm — including negative impacts on navigational safety interests, transportation interests, national security interests, commercial interests, and marine mammals — and in light of potential inadequacies in various environmental reviews required by the National Environmental Policy Act to lease or permit wind projects, the Secretary of the Interior, the Secretary of Agriculture, the Secretary of Energy, the Administrator of the Environmental Protection Agency, and the heads of all other relevant agencies, shall not issue new or renewed approvals, rights of way, permits, leases, or loans for onshore or offshore wind projects pending the completion of a comprehensive assessment and review of Federal wind leasing and permitting practices.  The Secretary of the Interior shall lead that assessment and review in consultation with the Secretary of the Treasury, the Secretary of Agriculture, the Secretary of Commerce, through the National Oceanic and Atmospheric Administration, the Secretary of Energy, and the Administrator of the Environmental Protection Agency.  The assessment shall consider the environmental impact of onshore and offshore wind projects upon wildlife, including, but not limited to, birds and marine mammals.  The assessment shall also consider the economic costs associated with the intermittent generation of electricity and the effect of subsidies on the viability of the wind industry.

(b)  In light of criticism that the Record of Decision (ROD) issued by the Bureau of Land Management on December 5, 2024, with respect to the Lava Ridge Wind Project Final Environmental Impact Statement (EIS), as approved by the Department of the Interior, is allegedly contrary to the public interest and suffers from legal deficiencies, the Secretary of the Interior shall, as appropriate, place a temporary moratorium on all activities and rights of Magic Valley Energy, LLC, or any other party under the ROD, including, but not limited to, any rights-of-way or rights of development or operation of any projects contemplated in the ROD.  The Secretary of the Interior shall review the ROD and, as appropriate, conduct a new, comprehensive analysis of the various interests implicated by the Lava Ridge Wind Project and the potential environmental impacts.

(c)  The Secretary of the Interior, the Secretary of Energy, and the Administrator of the Environmental Protection Agency shall assess the environmental impact and cost to surrounding communities of defunct and idle windmills and deliver a report to the President, through the Assistant to the President for Economic Policy, with their findings and recommended authorities to require the removal of such windmills.

(d)  The Attorney General may, as appropriate and consistent with applicable law, provide notice of this order to any court with jurisdiction over pending litigation related to any aspect of the Federal leasing or permitting of onshore or offshore wind projects or the Lava Ridge Wind Project, and may, in the Attorney General’s discretion, request that the court stay the litigation or otherwise delay further litigation, or seek other appropriate relief consistent with this order, pending the completion of the actions described in subsection (a) or subsection (b) of this section, as applicable.

This memorandum shall be implemented consistent with applicable law and subject to the availability of appropriations. 

This memorandum is not intended to, and does not, create any right or benefit, substantive or procedural, enforceable at law or in equity by any party against the United States, its departments, agencies, or entities, its officers, employees, or agents, or any other person. You are authorized and directed to publish this memorandum in the Federal Register.